Aim to complete Barapullah Phase-3 flyover by December: Delhi PWD Minister

14

New Delhi, May 12 (IANS) The Delhi government is pushing to complete the long-delayed Barapullah Phase-3 flyover by December this year, Public Works Department (PWD) Minister Parvesh Verma announced on Monday during a visit to the project site.

Describing it as a major infrastructure initiative, Verma said work has picked up pace after delays caused by pending payments and administrative hurdles under the previous government.

“This is a very big project. The company handling the construction had raised concerns about non-payment. We have cleared those dues, and you can see the progress — last time we visited, work was stalled, but now the bridge is almost ready,” Verma told reporters.

“We’re actively following up on the approvals needed to shift the trees. The previous government neglected this issue and failed to release contractor payments, causing major delays. We are now working to ensure the remaining work is completed at the earliest,” Verma added.

The third phase of the Barapullah elevated corridor project was to connect South Delhi to East Delhi. This project, which was started seven years ago, has not been completed yet, despite tall claims and promises. Efforts are also being made to increase the length of the Barapullah flyover through this project. The total length of the phase 1, 2 and 3 corridors of Barapullah flyover is 9.5 km.

The Barapullah Phase-3 corridor aims to provide signal-free travel between east Delhi’s Mayur Vihar-I and AIIMS in south Delhi by linking the new flyover with the existing Barapullah stretch at Sarai Kale Khan.

Though 98 per cent of the construction has been completed, the remaining work is held up due to pending approvals from the forest department for the relocation of nearly 200 trees. The project, which began in 2015, was initially scheduled for completion in 2017.

–IANS

sd/rad

Go to Source

Disclaimer

The information contained in this website is for general information purposes only. The information is provided by BhaskarLive.in and while we endeavour to keep the information up to date and correct, we make no representations or warranties of any kind, express or implied, about the completeness, accuracy, reliability, suitability or availability with respect to the website or the information, products, services, or related graphics contained on the website for any purpose. Any reliance you place on such information is therefore strictly at your own risk.

In no event will we be liable for any loss or damage including without limitation, indirect or consequential loss or damage, or any loss or damage whatsoever arising from loss of data or profits arising out of, or in connection with, the use of this website.

Through this website you are able to link to other websites which are not under the control of BhaskarLive.in We have no control over the nature, content and availability of those sites. The inclusion of any links does not necessarily imply a recommendation or endorse the views expressed within them.

Every effort is made to keep the website up and running smoothly. However, BhaskarLive.in takes no responsibility for, and will not be liable for, the website being temporarily unavailable due to technical issues beyond our control.

For any legal details or query please visit original source link given with news or click on Go to Source.

Our translation service aims to offer the most accurate translation possible and we rarely experience any issues with news post. However, as the translation is carried out by third part tool there is a possibility for error to cause the occasional inaccuracy. We therefore require you to accept this disclaimer before confirming any translation news with us.

If you are not willing to accept this disclaimer then we recommend reading news post in its original language.

MGID