Chennai, Nov 21 (IANS) The Greater Chennai Corporation (GCC) has identified several permanent encroachments, including apartment buildings, private hospitals, and clinics, during the flood mitigation survey, and the Revenue Department will issue notices for their removal.
Officials from the GCC confirmed that the notices will be followed by lawful eviction after submitting the survey report.
The corporation has removed temporary structures occupying 13,800 sq.m along the roads, facilitating the development of a new waterbody, which is being converted into a flood mitigation pond.
The survey was conducted after resident associations in suburban areas raised concerns over encroachments on waterbodies, leading to increased flooding.
Office bearers of the Singaperumal Koil residents’ association complained about encroachments on the Singaperumal Koil lake opposite the temple near GST Road.
Karvendhan, an IT professional, highlighted that many commercial buildings, including hotels and hospitals along GST Road, have encroached on the lake, exacerbating flood risks for residents.
He urged the Chennai Corporation to promptly remove temporary and permanent encroachments to address water stagnation and flooding.
In parallel, the GCC is working to increase the water storage capacity of several waterbodies in flood-prone areas.
Officials stated that efforts are underway to address water stagnation experienced during the 2023 monsoon season.
In Valasaravakkam’s SVS Nagar, the GCC plans to enhance the storage capacity of an existing waterbody by 60 per cent.
Currently, the waterbody holds 4.15 lakh cubic feet, and the area experienced four days of water stagnation during the 2023 monsoon.
Once completed, the project is expected to reduce flooding in SVS Nagar, Jai Nagar, Subramanya Nagar, and Ambedkar Salai.
The GCC also plans to connect the pond to stormwater drains from stretches such as Ambedkar Salai.
The corporation officials said that the immediate priority is to increase the capacity of Alapakkam Lake in Valasaravakkam, which has shrunk from 57.48 acres to 9.88 acres.
Its storage capacity will be raised from 4.2 million cubic feet to 5.2 million cubic feet, reducing flooding in Maduravoyal and Valasaravakkam.
The GCC will also enhance the capacity of Thaangal Keni in Sholinganallur from 3.25 million cubic feet to 16.25 million cubic feet.
This waterbody spans 1,10,000 sq.m of Meikal Poromboke land and is integral to the local drainage system.
The improvement is expected to mitigate flooding near Infosys IT Park and the Aavin production plant.
–IANS
aal/svn
Disclaimer
The information contained in this website is for general information purposes only. The information is provided by BhaskarLive.in and while we endeavour to keep the information up to date and correct, we make no representations or warranties of any kind, express or implied, about the completeness, accuracy, reliability, suitability or availability with respect to the website or the information, products, services, or related graphics contained on the website for any purpose. Any reliance you place on such information is therefore strictly at your own risk.
In no event will we be liable for any loss or damage including without limitation, indirect or consequential loss or damage, or any loss or damage whatsoever arising from loss of data or profits arising out of, or in connection with, the use of this website.
Through this website you are able to link to other websites which are not under the control of BhaskarLive.in We have no control over the nature, content and availability of those sites. The inclusion of any links does not necessarily imply a recommendation or endorse the views expressed within them.
Every effort is made to keep the website up and running smoothly. However, BhaskarLive.in takes no responsibility for, and will not be liable for, the website being temporarily unavailable due to technical issues beyond our control.
For any legal details or query please visit original source link given with news or click on Go to Source.
Our translation service aims to offer the most accurate translation possible and we rarely experience any issues with news post. However, as the translation is carried out by third part tool there is a possibility for error to cause the occasional inaccuracy. We therefore require you to accept this disclaimer before confirming any translation news with us.
If you are not willing to accept this disclaimer then we recommend reading news post in its original language.